February 22nd, 2010 [Dr.Srinath/A.S.Malinga, K.Pradeeban / CSE Research Lab]

I am writing a switch which will hide the existing menus from mooshabaya if enabled; by default mooshabaya will display all the menus. Dr.Srinath also asked to implement a screen scrapping component. And we will have to make it possible to run the workflow from xbaya itself instead of going to mashup server to invoke it from there. These are the milestones from March 11th demo.

Dr.Srinath asked to come up with a use case, which  will essentially cover all the use cases of Mooshabaya for the demo. He will fix a meeting with Dr.Sanjiva soon. The demo that we will prepare will be sent to Suresh Marru from IU. 

Since modifying Axiom's pom succeeded, I am currently trying to make mbaya a new carbon-orbit bundle, hence reverted the changes that made to axiom for testing.

We also had a discussion about Taverna and other workflow composers, which can be used instead of XBaya, though XBaya became our preferred choice since we are familiar with it and it is convenient when coming to integrate to mashup domain. Project updates and todos at the moment can be found here, where this depicts the overall view of the project.


March 24th, 2010

We had a meeting with the project's internal mentor Mrs.Vishaka Nanayakkara where we gave an overall idea and an update on the status of the project and got her thoughts and remarks.

We also demonstrated the project to the Project Coordinator Mr.Shantha Fernando and the project mentor Mrs.Vishaka Nanayakkara for the third formal project evaluations. I described and demonstrated the other input sources (files, feeds, and scraper), the XMLBeans Event generator for the known LEAD Event Types, and mbaya orbit bundle that makes XSUL messenger working as the monitoring module.


April 5th, 2010

We discussed the potential research paper for the project as well as the timeline with Mrs.Vishaka Nanayakkara, and got her suggestions and thoughts.


April 23rd, 2010 [Dr.Srinath/all/ CSE Research Lab]

We had a meeting with the mentor Dr.Srinath Perera where we gave the updates of the projects, discussed the further procedure of Mooshabaya, and the research paper.

May 26th, 2010 [Dr.Srinath/Research Lab]
We showed the screencasts, and showed the final draft paper and got his suggestions and consent. We got his thoughts on the research paper that we had submitted too.

May 27th, 2010
We discussed the draft report with the project's internal mentor, and got her consent and suggestions.